ScheduleCIS 422/522, Fall 2005
|
Project 1 begins September 27 (Tuesday of week 1) and is due October 19 (Wednesday of week 4).
Project 2 begins October 20 (Thursday of week 4) and is due November 23 (Wednesday of week 9).
The midterm is tentatively scheduled for 27 October.
Details of this schedule will change and be filled in as the term progresses. So far it is primarily project milestones; I am still working on ordering and scheduling of lecture topics.
Week (dates) | Tuesday | Thursday |
1 (27,29 Sept) | Introduction Select project; questionnaire |
Teamwork, scheduling. Form teams |
2 (4, 6 Oct) | 5 minute plan presentations. |
5 minute plan presentations. |
3 (11, 13 Oct) | 5 minutes status reports. | 5 minutes status reports. |
4 (18, 20 Oct) | Project 1due Wednesday. Discuss project 2. | Project 2 team formation and project discussions. |
5 (25, 27 Oct) | Project 2 product pitches. | (Michal in DC) |
6 (1, 3 Nov) | Project pitches - 10 minutes each. | |
7 (8, 10 Nov) | 5 minute project updates. | |
8 (15, 17 Nov) | 5 minute project updates. | |
9 (22 Nov) | Project 2 due | Holiday |
10 (29 Nov, 1 Dec) | Demos | Demos |
11 (exam week) |
Last edit: Mon, 26 September, 2005 / Version identifier: $Id: schedule.html,v 1.1 2005/09/26 20:42:08 michal Exp $